How to enable maintenance planning and scheduling |
|
|
|
|
|
Written by Terry Wireman
|
Maintenance
planning and scheduling initiatives start with a work order system. It
is essential to have the work order system used effectively so that all
maintenance activities are captured in the system. While the level of
detail that is captured may vary from company to company, the work
order system should track the information highlighted in the last newsletter
to insure there is a return on investment for using it; this includes
the ability to track labour data, materials data and contractor
information.
The work order should also be able to track this information to a
functional location, “building-floor-room” locator or a particular
piece of equipment. The work order system should then be able to
provide this information in a format that is can be utilized for
historical analysis.
Once the work order system is in place, the process for utilizing it
should be developed and detailed by the departments required to use it.
This includes decisions such as:
- Who can request work?
- What criterion determines the type of work?
- Who approves the work?
- Who assigns the priority?
When deciding who should request work, one of the considerations
should be proper training of the individuals to initialize a work
order. This could include computer training, software specific training
on the CMMS/EAM system. The goal is to insure that when work is
requested, the proper information is provided by the requestor. This
will enable the approver and planner of the work to understand what is
being requested so prompt and correct decisions can be made about the
request.
The next decision is the type of work that is being requested. If this
is clearly defined, it makes the planning of the work easier. For
example, is the work being requested an emergency or is it a normal job
that can be planned and scheduled. Clearly defining what constitutes an
“emergency” can eliminate much confusion in the work order process. For
example, guidelines such as the work must impact:
- Environmental, Health, Safety Standards
- Downtime criteria (cost, duration) will be exceeded
- Collateral equipment/ facility damage will occur
- Product or Service Quality will be impacted
Specifying and enforcing the work request (or notification) process
will prevent the planner from becoming involved in jobs where they add
little or no value. In many cases, a planner can become so involved in
emergency (reactive) work, that they perform very little actual
planning; in fact they become expediters or clerical assistants for a
supervisor.
Once the work has been correctly submitted (emergency or planned), it
is necessary for it to be approved. The approver of the requested work
may be an operations supervisor (for work submitted by operations
personnel) or a maintenance planner. In some organizations, any
employee is allowed to request work; however, without an approval
process, the planner may spend a considerable amount of time explaining
why some work cannot be performed. If a work order is sent to planning
and still has to be rejected, a detailed explanation of the reason for
the rejection should be sent to the requestor. This will insure that,
in the future, only legitimate work will be entered into the planning
process.
With this information provided, the work request is ready to be
converted to a work order and properly planned. What are the steps
involved in properly planning a work order? This will be the topic
covered in the next newsletter.